Action lists

Production, project delivery, and new work

1 promise at risk · 3 facilities reviewed

1 waiting for approval

Production

Material arrivals, production capacity, and delivery promises

350 MCM cabinet harnesses · delivery at risk

Summit Controls · GO 24193 · opened 07:42

Material readyNov 18
Planned finishNov 23
Customer promiseNov 20

How we know

  • Supplier ETA moved from Nov 13 to Nov 18 on PO 88314.
  • Columbus needs 144 h of qualified harness assembly work.
  • Review the available slots across facilities and the effect of moving work already in the schedule.

Next step

Update the supplier ETA and compare capacity before applying a revised plan.

Open production schedule →