Projects

Every job, its material dependencies, and the promise behind it

Open projects20
In production6
Awaiting material14
At risk1
Job / customerStatusFacilityLaborMaterial readyFinish / promise
In productionColumbus168 hNov 6Nov 11due Nov 13
In productionColumbus144 hNov 9Nov 12due Nov 20
At riskColumbus144 hNov 18Nov 23due Nov 20
Awaiting materialColumbus192 hNov 17Nov 19due Dec 4
Awaiting materialColumbus240 hNov 20Nov 30due Dec 4
Awaiting materialColumbus280 hNov 27Dec 4due Dec 11
Awaiting materialColumbus216 hDec 4Dec 11due Dec 18
In productionGreenville132 hNov 6Nov 13due Nov 13
In productionGreenville108 hNov 6Nov 13due Nov 13
Awaiting materialGreenville176 hNov 13Nov 19due Nov 20
Awaiting materialGreenville104 hNov 16Nov 24due Nov 27
Awaiting materialGreenville180 hNov 23Nov 30due Dec 4
Awaiting materialGreenville240 hNov 27Dec 7due Dec 11
Awaiting materialGreenville210 hDec 4Dec 11due Dec 18
In productionPhoenix150 hNov 6Nov 11due Nov 13
In productionPhoenix120 hNov 6Nov 13due Nov 13
Awaiting materialPhoenix128 hNov 13Nov 19due Nov 20
Awaiting materialPhoenix144 hNov 20Nov 25due Dec 4
Awaiting materialPhoenix180 hNov 27Dec 3due Dec 11
Awaiting materialPhoenix144 hDec 4Dec 11due Dec 18

20 of 20 projects

GO 24193At risk

Summit Controls

350 MCM cabinet harnesses

Quantity96
Labor144 h
Complete0%

Production milestones

Material availableNov 18

Lugs arrive Nov 18 · PO 88314

Build at ColumbusNov 19

Harness assembly · 144 h reserved

Planned completionNov 23

Continuity test, final inspection, and pack

Customer promiseNov 20

Morgan Lee

Job requirements

  • HRN-350-12 · 96 units
  • Harness assembly · qualified operations required
  • Columbus facility calendar applied
Priority · Standard