Projects
Every job, its material dependencies, and the promise behind it
Open projects20
In production6
Awaiting material14
At risk1
| Job / customer | Status | Facility | Labor | Material ready | Finish / promise |
|---|---|---|---|---|---|
| In production | Columbus | 168 h | Nov 6 | Nov 11due Nov 13 | |
| In production | Columbus | 144 h | Nov 9 | Nov 12due Nov 20 | |
| At risk | Columbus | 144 h | Nov 18 | Nov 23due Nov 20 | |
| Awaiting material | Columbus | 192 h | Nov 17 | Nov 19due Dec 4 | |
| Awaiting material | Columbus | 240 h | Nov 20 | Nov 30due Dec 4 | |
| Awaiting material | Columbus | 280 h | Nov 27 | Dec 4due Dec 11 | |
| Awaiting material | Columbus | 216 h | Dec 4 | Dec 11due Dec 18 | |
| In production | Greenville | 132 h | Nov 6 | Nov 13due Nov 13 | |
| In production | Greenville | 108 h | Nov 6 | Nov 13due Nov 13 | |
| Awaiting material | Greenville | 176 h | Nov 13 | Nov 19due Nov 20 | |
| Awaiting material | Greenville | 104 h | Nov 16 | Nov 24due Nov 27 | |
| Awaiting material | Greenville | 180 h | Nov 23 | Nov 30due Dec 4 | |
| Awaiting material | Greenville | 240 h | Nov 27 | Dec 7due Dec 11 | |
| Awaiting material | Greenville | 210 h | Dec 4 | Dec 11due Dec 18 | |
| In production | Phoenix | 150 h | Nov 6 | Nov 11due Nov 13 | |
| In production | Phoenix | 120 h | Nov 6 | Nov 13due Nov 13 | |
| Awaiting material | Phoenix | 128 h | Nov 13 | Nov 19due Nov 20 | |
| Awaiting material | Phoenix | 144 h | Nov 20 | Nov 25due Dec 4 | |
| Awaiting material | Phoenix | 180 h | Nov 27 | Dec 3due Dec 11 | |
| Awaiting material | Phoenix | 144 h | Dec 4 | Dec 11due Dec 18 |
20 of 20 projects
GO 24193At risk
Summit Controls
350 MCM cabinet harnesses
Quantity96
Labor144 h
Complete0%
Production milestones
Material availableNov 18
Lugs arrive Nov 18 · PO 88314
Build at ColumbusNov 19
Harness assembly · 144 h reserved
Planned completionNov 23
Continuity test, final inspection, and pack
Customer promiseNov 20
Morgan Lee
Job requirements
- HRN-350-12 · 96 units
- Harness assembly · qualified operations required
- Columbus facility calendar applied